MISTAKES WITH PANEL BUILD AND LACK OF DRAWINGS

Summary

Logged Date
2026-03-25
Owner
Rob Preston
Party
LME
Area
Panel builds
Priority
Standard
Resolved Date
2026-05-05
Signed Off By
Rob Preston

Problem

Links missing , telemetry terminals wrong way round , no drawings

Investigation And Action

Corrective Action

Feedback sent to supplier; FAT/test evidence reviewed with supplier.

Customer Feedback

-

Root Cause

Supplier delivered incomplete/incorrect build and missing documentation; internal QA needed to verify FAT and drawings.

Preventative Action

Ensure purchase orders specify required drawings and FAT as minimum; supplier feedback loop established.

Review Effectiveness

Supplier engaged and corrective feedback issued; team concluded close.

AI Investigation Review

Builds an evidence-based review from this NCL, status history, related NCLs, and relevant communications. The report is stored here and emailed to Luke, Rob and Michelle.

No AI investigation review has been stored for this record yet.
Status Update

Use this panel for all status changes. Main edit form does not change status.

Status History
FromToChanged AtByNote
In ReviewResolved2026-05-05 21:11:19management reviewTranscript summary: Panel build issues (missing links, telemetry terminals, no drawings). Feedback was provided to supplier and FAT records reviewed; team agreed to close once supplier feedback confirmed. Closed after supplier feedback and FAT review. Root cause check: strong - Direct supplier quality/delivery issues identified and supplier engaged with QA evidence review; actions completed to supplier feedback stage.
InitialIn Review2026-03-30 09:37:54anonymous-
-Initial2026-03-26 18:08:51anonymous-