ISO

NCL-2026-0042

Drawings for vent not accurate

Summary

Logged Date
2026-04-17
Owner
Mark Marriott
Party
Haigh
Area
Design
Priority
Standard
Resolved Date
-
Signed Off By
-

Problem

Paused drilling of holes due to drawings not quite right. For review

Investigation And Action

Corrective Action

Pause works until drawings updated and validated; Elliot to amend as-built drawings, print and reissue; control panel to be checked against updated GA prior to delivery.

Customer Feedback

-

Root Cause

Out-of-date or inaccurate design/drawings not reflecting on-site conditions.

Preventative Action

Implement drawing version control and require confirmation of latest drawings prior to on-site work.

Review Effectiveness

Immediate corrective pause applied and drawings amended; effectiveness depends on adoption of version control.

AI Investigation Review

Builds an evidence-based review from this NCL, status history, related NCLs, and relevant communications. The report is stored here and emailed to Luke, Rob and Michelle.

No AI investigation review has been stored for this record yet.
Status Update

Use this panel for all status changes. Main edit form does not change status.

Status History
FromToChanged AtByNote
In ReviewIn Review2026-06-01 08:59:51management reviewTranscript summary: Reviewed again in meeting. Drawing inaccuracies caused paused drilling/works; Elliot tasked to amend as-built drawings and reissue. Decision to keep ticket open until updated drawings validated and control panel delivery confirmed. 2026-06-01 meeting: drawing inaccuracies re-affirmed; Elliot assigned to produce amended as-built drawings; ticket left open for validation. Root cause check: strong - The team traced the issue directly to inaccurate/out-of-date drawings and assigned an immediate corrective action (Elliot to amend drawings).
InitialIn Review2026-06-01 07:09:31management reviewTranscript summary: Drawings for vent not accurate; drilling was paused and team confirmed not to start until drawings corrected. Design review carried out. Mark flagged inconsistency and drilling paused; drawing updates to follow. Root cause check: strong - Issue identified early, corrective action taken; root cause (inaccurate drawings) direct and addressable.
-Initial2026-04-17 13:36:35anonymous-